Procurement Management - Complete Workflow

Document ID: PROC-WF-001 Version: 1.0 Last Updated: May 2026


πŸ”„ Complete Procurement Workflow

The procurement process consists of 8 major stages, each with specific activities and approval gates.


πŸ“ Stage 1: Requisition Submission

Overview

Authorized personnel submit a purchase request with all necessary details. This is the starting point of the entire procurement cycle.

Process Flow

  1. Initiator accesses the Procurement Module
  2. Selects β€œCreate New Requisition”
  3. Enters the following details:
  4. Reviews all information for accuracy
  5. Submits requisition for approval

Key Activities

Roles Involved

Duration

Approval Gate

None - Direct submission to next stage

System Validations

Error Handling

Error Resolution
Missing required fields System prompts to complete
Invalid budget code Dropdown selection provided
Insufficient budget Warning displayed, can proceed
Invalid attachment Format validation (PDF, Excel, Images only)

πŸ“ Stage 2: Department Head Approval

Overview

The department head reviews the requisition for departmental fit and appropriateness. This ensures that the purchase aligns with department needs and priorities.

Process Flow

  1. Department Head receives notification (Email + In-App)
  2. Accesses pending requisition
  3. Reviews:
  4. Decision Options:
  5. Adds comments (mandatory for reject/hold)
  6. Submits decision

Key Activities

Roles Involved

Duration

Approval Gate

CRITICAL - Requisition cannot proceed without approval

Escalation

If SLA exceeded: - Day 4: Automated reminder email - Day 5: Escalation to Finance Manager - Day 7: Auto-approval option available

System Validations

Notification Rules

Decision Who Gets Notified When
Approved Finance Manager, Requisitioner Immediately
Rejected Requisitioner, System Manager Immediately
Modified Requisitioner Immediately
Held Finance Manager, Requisitioner After 2 days

πŸ“ Stage 3: Finance Manager Review

Overview

Finance Manager reviews budget compliance, financial feasibility, and overall financial impact. This ensures fiscal responsibility and policy compliance.

Process Flow

  1. Finance Manager receives requisition
  2. Reviews:
  3. Validation Checks:
  4. Decision Options:
  5. Submits decision with supporting notes

Key Activities

Roles Involved

Duration

Approval Gate

CRITICAL - Controls financial access

Budget Rules

Budget Check = Requested Cost <= (Total Budget - Committed - Spent)

If Check Fails:
  - Show available budget
  - Suggest cost reduction
  - Option to apply for budget increase

System Calculations

Notification Pattern

Scenario Action Notification
Budget OK Auto-approve Finance Manager (info only)
Budget Low Manual review required Finance Manager (alert)
Budget Exceeded Reject Requisitioner + Dept Head
Policy Issue Escalate Senior Finance Officer

πŸ“ Stage 4: Authority Officer Final Approval

Overview

For high-value purchases or special items, authority officer provides final approval. This ensures proper authorization for significant expenditures.

Process Flow

  1. Authority Officer receives notification
  2. Conditionally triggered if:
  3. Reviews:
  4. Final Decision:
  5. Submits with authority signature

Key Activities

Roles Involved

Duration

Approval Gate

CRITICAL - Final authorization gate before procurement

Authorization Limits

Approval Authority by Amount:

Department Head
  └─ Up to $5,000

Finance Manager
  └─ Up to $25,000

Authority Officer
  └─ Up to $100,000

Procurement Committee
  └─ Above $100,000

Conditional Approval Options


πŸ“ Stage 5: Purchase Order Generation

Overview

Once all approvals are obtained, the system automatically generates and sends purchase orders to vendors. This stage initiates the actual purchasing process.

Process Flow

  1. Procurement Officer receives auto-notification
  2. Vendor Selection:
  3. PO Generation:
  4. PO Customization:
  5. PO Transmission:
  6. Confirmation Tracking:

Key Activities

Roles Involved

Duration

System Validations

PO Content Checklist

Vendor Communication

Email Template:
Subject: Purchase Order [PO#] - [Item Description]

Body:
- PO Details
- Delivery Instructions
- Contact Information
- Payment Terms
- Attachment: PDF of PO
- Request for Acknowledgment

πŸ“ Stage 6: Order Status & Tracking

Overview

The system maintains real-time tracking of ordered items from vendor through delivery. This provides visibility and enables proactive exception management.

Process Flow

  1. Order Created - Initial status β€œOrdered”
  2. Vendor Acknowledgment - Status β€œConfirmed”
  3. Stock Notification - Vendor indicates item ready
  4. Shipment Dispatch - Status β€œIn Transit”
  5. Tracking Update - Real-time tracking via carrier
  6. Delivery Expected - ETA notification sent
  7. Delivery Alert - Notify receiving department

Tracking Activities

Roles Involved

Duration

Status Transitions

Ordered
  β”œβ”€ Confirmed (by vendor)
  β”œβ”€ In Transit (from warehouse)
  β”œβ”€ Out for Delivery
  β”œβ”€ Delivery Attempted
  β”œβ”€ Delivered
  β”œβ”€ Received
  └─ Cancelled (if needed)

Exception Paths:
β”œβ”€ On Hold (awaiting payment/approval)
β”œβ”€ Delayed (past promised delivery)
β”œβ”€ Returned (to vendor)
└─ Rejected (not meeting specs)

Notification Rules

Event Notification Recipients
Order Confirmed Email Requisitioner, Dept Head
Shipment Dispatched Email Goods Receipt Clerk
Delivery Expected Email + Alert All stakeholders
Delayed (>2 days) Alert Procurement Officer
Delivered Email Requisitioner
Exceptional Delay Escalation Senior Procurement

Tracking Data

Proactive Management


πŸ“ Stage 7: Goods Receipt & Inspection

Overview

When goods arrive, they are inspected for quality, quantity, and condition. This stage ensures received items match the purchase order and are acceptable.

Process Flow

  1. Delivery Received - Goods Receipt Clerk notified
  2. Unload & Initial Check:
  3. Barcode Scanning:
  4. Detailed Inspection:
  5. Decision:
  6. System Update:
  7. Notification:

Key Activities

Roles Involved

Duration

Approval Gate

IMPORTANT - Confirms receipt for invoice processing

Inspection Checklist

Physical Inspection:
[ ] Item count matches PO quantity
[ ] Packaging condition acceptable
[ ] No visible damage
[ ] Serial numbers recorded
[ ] Batch/lot numbers recorded

Quality Inspection:
[ ] Matches specifications
[ ] Correct version/model
[ ] Documentation included
[ ] Expiry date valid (if applicable)
[ ] Testing passed (if required)

Condition Assessment:
[ ] No physical damage
[ ] All parts included
[ ] Proper labeling
[ ] Safe to store/use
[ ] Special handling not needed

Documentation:
[ ] Packing slip present
[ ] Quality certificates included
[ ] Warranty information included
[ ] User manuals included
[ ] Invoice paperwork complete

Issue Resolution Matrix

Issue Action Escalation
Quantity Short Partial receipt + vendor follow-up If >10%
Damaged Items Quarantine + photo + vendor claim If >5 items
Wrong Item Reject + vendor notification Immediate
Quality Failure Reject + incident report Immediate
Missing Docs Accept with comment + vendor follow-up If critical
Expiry Soon Quarantine + urgent use notification If <30 days

Goods Receipt Report


πŸ“ Stage 8: Invoice Processing & Three-Way Match

Overview

When the vendor invoice is received, it is matched against the PO and goods receipt to ensure accuracy before payment. This critical process prevents overpayment and fraud.

Process Flow

  1. Invoice Receipt:

  2. Invoice Entry:

  3. Three-Way Matching:

    Comparison Required:
    β”Œβ”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”
    β”‚   PO (Quantity & Price)                β”‚
    β”‚           ∩                            β”‚
    β”‚   Goods Receipt (Actual Received)      β”‚
    β”‚           ∩                            β”‚
    β”‚   Invoice (Amount & Terms)             β”‚
    β””β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”˜
    
    All three must match:
    - Quantity: PO β‰ˆ Receipt β‰ˆ Invoice
    - Price: PO β‰ˆ Invoice
    - Description: All match exactly
  4. Matching Validation:

  5. Exception Handling:

  6. Resolution:

  7. Approval:

Key Activities

Roles Involved

Duration

Approval Gate

CRITICAL - Controls payment authorization

Matching Rules

EXACT MATCH (Auto-Approve):
- Qty variance: 0%
- Price variance: 0%
- All quantities equal

ACCEPTABLE MATCH (Review):
- Qty variance: 0-5%
- Price variance: 0-2%
- Amount variance: 0-$50

UNACCEPTABLE (Reject/Hold):
- Qty variance: >5%
- Price variance: >2%
- Amount variance: >$50 or >3%

Common Discrepancies & Solutions

Discrepancy Cause Solution
Qty variance Partial shipment Update PO to received qty
Unit price higher Unauthorized price change Reject, contact vendor
Unit price lower Negotiated discount Accept, update contract
Extra charges (shipping) Legitimate additional cost Match if on PO
Tax included Regional tax variation Accept if allowable
Early invoice Vendor invoiced before delivery Hold until receipt
Late invoice Delayed vendor processing Accept if within terms

Invoice Matching Report

Three-Way Match Exception Report

PO Number: [______]
Vendor: [______]
Invoice Date: [______]

Matching Details:
β”œβ”€ PO Qty: [__] vs Receipt Qty: [__] vs Invoice Qty: [__]
β”œβ”€ PO Price: $[__] vs Invoice Price: $[__]
β”œβ”€ PO Total: $[__] vs Invoice Total: $[__]
β”œβ”€ Variance Amount: $[__] ([__]%)
└─ Variance Reason: [____________________]

Exception Details:
β”œβ”€ Exception Type: [ ] Qty [ ] Price [ ] Amount
β”œβ”€ Severity: [ ] Minor [ ] Major [ ] Critical
β”œβ”€ Status: [ ] Approved [ ] Rejected [ ] On Hold
└─ Approver: [_____________]

Resolution:
β”œβ”€ Invoice Adjusted: [ ] Yes [ ] No
β”œβ”€ Adjustment Amount: $[__]
β”œβ”€ Reason: [_________________________]
└─ Final Status: [ ] Ready for Payment [ ] Rejected

πŸ“ Stage 9: Payment Processing

Overview

Once invoices are matched and approved, payments are processed through the selected payment method. This stage completes the financial transaction cycle.

Process Flow

  1. Payment Preparation:
  2. Payment Method Selection:
  3. Vendor Master Verification:
  4. Payment Batch Creation:
  5. Payment Authorization:
  6. Payment Execution:
  7. Confirmation & Recording:
  8. Reconciliation:

Key Activities

Roles Involved

Duration

Approval Gate

CRITICAL - Controls financial outflow

Payment Method Details

Check Payment

Process:
1. Invoice selected
2. Check details entered
3. Check printed (check stock required)
4. Signature line(s) required
5. Check mailed to vendor
6. Record in system
7. Clearing via bank

Timeline:
- Processing: 1 day
- Clearing: 5-10 days

Cost:
- Check printing: $0.50-1.00 per check
- Postage: $0.68 per check
- Total cost: ~$1.20 per check

Bank Transfer (ACH/WIRE)

Process:
1. Invoice selected
2. Vendor bank details confirmed
3. Wire/ACH initiated
4. Bank processes
5. Confirmation received
6. Record in system

Timeline:
- ACH: 1-3 business days
- WIRE: Same day

Cost:
- ACH: $0.25-1.00 per transfer
- WIRE: $10-30 per transfer
- Total: $0.25-30 per transaction

Advantages:
βœ“ Fast (WIRE)
βœ“ Secure
βœ“ No physical mail
βœ“ Automatic clearing
βœ“ Trackable

Credit Card

Process:
1. Invoice amount charged to corp card
2. Batch settlement with bank
3. Monthly statement processed
4. GL coded to department
5. Vendor notified (optional)

Timeline:
- Processing: 1 day
- Settlement: 2-3 business days
- Clearing: 3-5 business days

Cost:
- Processing fee: 1.5-3% of amount
- Annual fee: $0-300
- Rewards: 0.5-2% cash back

Advantages:
βœ“ Consolidated billing
βœ“ Potential rewards
βœ“ Float benefit (30 days)
βœ“ Detailed reporting

E-Payment Platforms

Process:
1. Vendor registered on platform
2. Invoice amount added to platform
3. Vendor notified of pending payment
4. Vendor confirms receipt
5. Auto settlement to vendor's account
6. Record in system

Timeline:
- Processing: 1-2 business days
- Settlement: 1-3 business days

Cost:
- Per transaction: $0.50-2.00
- Monthly: $0-50
- Percentage: 0.5-1%

Examples:
- Coupa
- Ariba
- Mastercard VOP
- Bottomline

Payment Batch Report

Payment Authorization Batch

Batch Number: [_____]
Batch Date: [_______]
Payment Method: [ ] Check [ ] Transfer [ ] Card [ ] E-Payment

Batch Summary:
β”œβ”€ Number of Invoices: [__]
β”œβ”€ Total Amount: $[_____,__]
β”œβ”€ By Department: [Chart]
β”œβ”€ By Vendor (Top 5): [Chart]
└─ By Payment Method: [Breakdown]

Approvals:
β”œβ”€ Prepared by: [________] Date: [____]
β”œβ”€ Reviewed by: [________] Date: [____]
β”œβ”€ Approved by: [________] Date: [____]
└─ Authorized by: [________] Date: [____]

Execution:
β”œβ”€ Executed Date: [____]
β”œβ”€ Execution Method: [Check/Wire/etc]
β”œβ”€ Confirmation #: [_________]
β”œβ”€ Tracking Status: [ ] Pending [ ] Completed
└─ Cleared Date: [____] (when confirmed by bank)

Exception Invoices:
β”œβ”€ Held back: [__]
β”œβ”€ Reasons: [_______________________]
└─ Resolution: [_____________________]

πŸ“ Stage 10: Closure & Archival

Overview

After successful payment and reconciliation, the procurement transaction is closed and archived. This ensures complete documentation and enables future reference and analysis.

Process Flow

  1. Pre-Closure Verification:
  2. Closure Activities:
  3. Documentation Package:
  4. System Archival:
  5. Reporting & Analysis:
  6. Record Retention:

Key Activities

Roles Involved

Duration

Closure Checklist

Pre-Closure Requirements:
[ ] Payment status = "Cleared"
[ ] All invoices matched
[ ] No outstanding disputes
[ ] Goods receipt complete
[ ] All approvals obtained
[ ] No holds or flags
[ ] Documentation complete
[ ] Vendor confirmed receipt

Closure Documentation:
[ ] Requisition in system
[ ] All approval comments captured
[ ] PO in system
[ ] GR in system
[ ] Invoice in system
[ ] Payment record in system
[ ] Exception reports (if any)
[ ] Photos/attachments saved

System Tasks:
[ ] PO status = "Closed"
[ ] Invoice status = "Paid"
[ ] Budget reconciled
[ ] GL posting completed
[ ] Supplier performance updated
[ ] Historical record created
[ ] Archived to long-term storage

Quality Review:
[ ] Cycle time acceptable
[ ] Cost within budget
[ ] No compliance issues
[ ] Supplier performance rated
[ ] Lessons learned captured

Metrics Calculation

Procurement Cycle Time:
= Closure Date - Requisition Date

Cost Performance:
= (Actual Cost - Budgeted Cost) / Budgeted Cost

Quality Score:
= (100 - Exception Count*10) if <100 else 100

Supplier Performance:
= (On-Time Delivery + Quality Score + Cost Competitiveness) / 3

Process Efficiency:
= (Automated Approvals / Total Approvals) * 100

Historical Analysis

Archive Access


πŸ”„ Complete Workflow Summary

PROCUREMENT WORKFLOW - Visual Summary

    β”Œβ”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”
    β”‚  STAGE 1: REQUISITION SUBMISSION                   β”‚
    β”‚  Requisitioner creates & submits purchase request   β”‚
    β””β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”¬β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”˜
                     β”‚
                     β–Ό
    β”Œβ”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”
    β”‚  STAGE 2: DEPARTMENT HEAD APPROVAL                 β”‚
    β”‚  Department Head reviews & approves requisition     β”‚
    β””β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”¬β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”˜
                     β”‚
                     β–Ό
    β”Œβ”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”
    β”‚  STAGE 3: FINANCE MANAGER REVIEW                   β”‚
    β”‚  Finance validates budget & financial compliance   β”‚
    β””β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”¬β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”˜
                     β”‚
                     β–Ό
    β”Œβ”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”
    β”‚  STAGE 4: AUTHORITY OFFICER APPROVAL               β”‚
    β”‚  (If amount exceeds limit or special items)        β”‚
    β””β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”¬β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”˜
                     β”‚
                     β–Ό
    β”Œβ”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”
    β”‚  STAGE 5: PURCHASE ORDER GENERATION                β”‚
    β”‚  Procurement creates & sends PO to vendor          β”‚
    β””β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”¬β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”˜
                     β”‚
                     β–Ό
    β”Œβ”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”
    β”‚  STAGE 6: ORDER TRACKING                           β”‚
    β”‚  Monitor order status & shipment progress          β”‚
    β””β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”¬β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”˜
                     β”‚
                     β–Ό
    β”Œβ”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”
    β”‚  STAGE 7: GOODS RECEIPT & INSPECTION               β”‚
    β”‚  Receive goods, inspect, and verify against PO     β”‚
    β””β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”¬β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”˜
                     β”‚
                     β–Ό
    β”Œβ”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”
    β”‚  STAGE 8: INVOICE PROCESSING                       β”‚
    β”‚  Match invoice with PO & receipt (3-way match)     β”‚
    β””β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”¬β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”˜
                     β”‚
                     β–Ό
    β”Œβ”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”
    β”‚  STAGE 9: PAYMENT PROCESSING                       β”‚
    β”‚  Process payment via selected method               β”‚
    β””β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”¬β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”˜
                     β”‚
                     β–Ό
    β”Œβ”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”
    β”‚  STAGE 10: CLOSURE & ARCHIVAL                      β”‚
    β”‚  Close transaction, archive records, update stats  β”‚
    β””β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”€β”˜

πŸ“Š Workflow Statistics

Metric Target Typical SLA
Req. to Approval 5 days 3-5 days 10 days
Approval to PO 2 days 1-2 days 5 days
Order to Receipt 15 days 5-30 days Based on vendor
Invoice to Payment 10 days 5-10 days 30 days
Total Cycle Time 32 days 20-50 days 60 days